Discussion on Modification of CPE Process
-
-
Abstract
Described here in the essay are the currently-used main operation steps of the CPE pipe mill.Relevant modification suggestions are put forward,including on-line mandrel extracting with a clasp(block fork),on-line mandrel loosening by planetary mandrel loosening mill,off-line pipe extracting by extracting mill,replacing the 3-roll die with the 4-roll die,and pointing via spinning process to reduce metal loss from cropping,etc. Relevant analysis leads to the following conclusion. Thanks to the on-line mandrel extracting/loosening operation steps,the manufacturing process flow will be shortened,the shell temperature raised,and the mandrel service span expanded,while due to replacement of the 3-roll die with the 4-roll die,the inner profile of the pipe as sized(reduced) will be turned from“the hexagonal”into“the octagonal”,and thus the pipe’s wall thickness accuracy will be improved.
-
-