UOE Welded Pipe Mill Stock Control in Mill Supervision Mode
-
-
Abstract
All the major elements as affecting fast finished product dispatch activities are analyzed and discussed on the basis of characteristics of the layout of the UOE welded pipe production line and the process path for the purpose of optimizing control of the mill stock of the UOE welded pipes so as to finally satisfy the actual need for whole-course mill supervision of the UOE pipe project at Baoshan Iron & steel Co.,Ltd. Such elements include structure of property inspection (analysi)s,inspection/analysis cycle,and finished product inspection-application cycle,etc. Accordingly, relevant measures for control of finished product management cycle of UOE welded pipes are proposed. Thanks to implementation of the T1 -T5 cycle management control actions,the UOE welded pipe stocking period is in general obviously shortened,and the periodic compliance rate is greatly enhanced.
-
-